中文字幕第一页在线无码_成人免费毛片在线观看_亚洲一区无码中文字幕乱码_欧美国产日韩久久mv

Anchor bolt

Home > Products > Anchor bolt
L Bolt

CATEGORY:L Bolt

+86-310 - 6880555 Order

Product details

1. One time embedding method: When pouring concrete, embed the L bolt. When the tower is controlled by overturning, the L bolt should be buried in one go.
2. Reserved hole method: The equipment is in place, the holes are cleaned, the L bolt are placed in the holes, the equipment is positioned and aligned, and then non shrinkage fine aggregate concrete one level higher than the original foundation is poured and compacted. The distance from the center of the buried L bolt to the edge of the foundation should not be less than 2d (d is the diameter of the L bolt), and should not be less than 15mm (when d ≤ 20, it should not be less than 10mm), and should not be less than half of the width of the anchor plate plus 50mm. When the above requirements cannot be met, appropriate measures should be taken to strengthen it. The diameter of the L bolt used in the structure should not be less than 20mm. When subjected to earthquake action, double nuts should be used for fixation, or other effective measures should be taken to prevent loosening, but the anchorage length of the L bolt should be increased by 5 days compared to the anchorage length under non earthquake action.
The installation plan of L bolt: Treatment of loose L bolt in the foundation. When tightening the L bolt, the bolts may be pulled out. At this time, the bolts should be adjusted to their original position first, and the foundation around the bolts should be excavated enough. Then, two U-shaped steel bars should be welded vertically and horizontally on the bolts. Finally, the pit should be cleaned with water and grouted. After the concrete solidifies to the design strength, the deviation of the L bolt can be tightened. The treatment method for deviation of the L bolt is roughly the same as that for dead L bolt, except that the L bolt can be pulled out for treatment. If the bolt is too long, a section can be cut off on the machine tool and threaded again; If the bolt is too short, it can be extended by hot forging method; If the position does not match, use the bending method to correct it.
Application industry: Suitable for various equipment fixation, steel structure foundation embedded parts, street lights, traffic signs, pump, boiler installation, heavy equipment embedded fixation, etc.

Related products

  • L Bolt
    L Bolt

    1. One time embedding method: When pouring concrete, embed the L bolt. When the tower is controlled ...

    View more
  • Hook bolt
    Hook bolt

    1. One time embedding method: When pouring concrete, embed the hook bolt. When the tower is controll...

    View more
  • Hook bolt
    Hook bolt

    1. One time embedding method: When pouring concrete, embed the hook bolt. When the tower is controll...

    View more

Prev:Hook bolt

Next:No more

崇义县| 永寿县| 克拉玛依市| 竹山县| 尉氏县| 柳州市| 长武县| 景宁| 交口县| 礼泉县| 诸城市| 汽车| 旬邑县| 玛沁县| 辰溪县| 化德县| 陆川县| 亚东县| 黑水县| 青阳县| 平定县| 淳安县| 体育| 新竹县| 肥乡县| 五原县| 岗巴县| 新绛县| 绥芬河市| 绥棱县| 文山县| 寻乌县| 绵竹市| 徐州市| 大宁县| 微山县| 西畴县| 万年县| 外汇| 鄢陵县| 石景山区|